#3 M2G Advanced Boiler Load controls were installed for the Powerscourt Resort and Spa in Co. Wicklow in January 2018

This contract fell under the EEOS scheme and the work was fully sponsored by Bord Gais

Analysis of the pre and post weather corrected consumption indicated a 6% reduction in oil consumption amounting to savings of c. €27,335 p.a.

With no maintenance or repair requirements whatsoever this was a significant win for this 5-Star Hotel Resort

M2G Installation on #3 Powerscourt Boilers